Packaging Machine Commissioning

Commissioning is everything between an installed packaging machine and an accepted one: proving it runs safely, tuning it on your product, and passing a run.

It starts once the machine is set, leveled, connected to power and air and switched on — everything before that is installation — and it ends at handover, with the run passed, the documents delivered and the open items listed with owners.

What the Plant Must Have Ready Before Commissioning Starts

Four things have to be ready before commissioning starts: product, packaging material, people and decisions.

Have the product and the packaging material on site at production spec and in production quantity, and keep to the film, pouch and product definitions the factory acceptance test used. A film changed for price after the FAT is a new format and gets tested as one.

Have the neighbouring machines set, conveyor heights matched and control signals wired. Assign operators and maintenance staff for the whole period.

Name one startup lead from your own staff to prioritise issues, approve or reject workarounds and hold the go/no-go for the acceptance run. Then read the contract: under ORGALIME S 2012, the general conditions much European machinery supply is written on, acceptance tests are carried out at the place of manufacture unless otherwise agreed — so check that a run on your own floor, and the technician days it takes, is something you bought.

Dry Commissioning: Prove Motion, Safety and Signals Before Product

The machine runs empty first, because a fault found with product in it costs cleaning, waste and sometimes a contaminated batch.

Confirm at the start that the machine, the fitted format parts and the loaded recipe are the ones you ordered. Then prove the safety functions — emergency stops, guards, interlocks, alarms and a restart that takes a deliberate action — before anything moves at speed.

Jog the motors and conveyors in the documented direction, check each sensor with the bags or containers it will actually see, and pass empty packs or dummies through every transfer point. Exercise the handshakes with the neighbours next — a stop from an upstream fault, a restart after a downstream accumulation — and only then let it run automatically at low speed. Record every fault with its correction and the retest that cleared it.

While you debug, work to lockout/tagout, not to the panel stop. Isolate at the disconnect, bleed the compressed air and release stored energy before a hand goes into the machine.

Product Commissioning: One Machine, Then Each Handoff, Then the Line

Real product goes in in stages: one machine running stable first, then each handoff, then the whole line at the agreed speed.

On a form-fill-seal or pre-made bag machine, the tuning points are film tension and tracking, seal temperature, dwell and jaw pressure, fill volume, registration and cut position, bag length and conveyor speed. Change one at a time and write down the values that held.

Commission the joints next: weigher-to-bagger timing, bagger-to-checkweigher spacing, cartoner infeed and the accumulation between them. Where a transfer tips, drops or jams a pack, fix it mechanically with a guide, a height or a transfer plate.

Run the line last and judge it by finished packs off the end.

Site Acceptance: The Run-at-Rate That Decides Pass or Fail

The acceptance run is judged against conditions written before it starts: which SKU or SKU range, at what speed, for how long, with which crew, how packs are sampled, and how much defect and downtime are allowed.

Let your own crew run it, with the supplier’s technician observing and stepping in only on safety.

“Seals pass ASTM F88” is not a criterion: the method measures a seal’s peel force and failure mode, and the minimum value has to come from your pack specification.

Fill accuracy has to name a market’s plan. NIST Handbook 133 allows no pack in a sample of 12 or 24 to fall short by more than the maximum allowable variation, while OIML R 87 tolerates 2.5 % of a group past the tolerable deficiency and none past twice it.

Beyond steady state, the run includes a timed format change and the abnormal cases: starved infeed, blocked discharge, missing component, rejected pack, sensor fault, emergency stop and recovery.

Log rejects, stops, alarms, adjustments and restarts, then split what the run turned up into critical failures and punch-list items, each with an owner, a correction and a retest condition.

Handover: Documents, Operator Training and the Warranty Clock

Handover is a package, a signature and a list of what is still open — and the warranty clock has most likely been running since well before that signature. ORGALIME S 2012 limits the supplier’s liability to defects appearing within one year from delivery, so the weeks between the machine landing and the acceptance run are warranty already spent, unless your contract ties the guarantee to acceptance.

For a CE-marked machine, part of the package is a legal minimum: the instruction manual, the drawings and diagrams needed to use, maintain and check the machine, the instructions for putting it into service, and the maintenance and adjustment work it leaves to you.

PLC and HMI backups, the approved setup records and recipes, training records and the open-items list with owners and dates arrive only because your purchase order asked for them.

Training is its own activity inside the same visit: commissioning is finished when the machine passes, training when your operators have themselves demonstrated normal production, a controlled stop, safe recovery, a changeover, cleaning and basic fault clearing.

Before the technician flies home, take the acceptance run’s figures as the line’s OEE baseline, put the preventive-maintenance schedule into the plant’s system and book a review of the line against that baseline.

    Comments are closed

    Soontact provides complete packaging solutions for manufacturers worldwide. Contact our packaging engineers to discuss your specific products, production volumes, and packaging material requirements.

    We offer machine demonstrations, application testing, and detailed proposals that address your particular operational needs.

    Get Your Custom Packaging Solution

    Tell us about your product and production needs. Our engineers will recommend the right machine configuration for your application.

    We only use your details to reply to this request.